PROJECT PLANNING PRACTICES AND PERFORMANCE OF HORN OF AFRICA GATEWAY DEVELOPMENT PROJECT IN KENYA

Sandra Muyoka Wafula, Dr. Yusuf Muchelule

Abstract


Purpose: To examine the effect of project planning practices on performance of Horn of Africa Gateway Development Project in Kenya.

Methodology: The current study adopted a descriptive survey design. The target population included the series of projects that are under the HoAGDP which included: a 350-kilometer road of the corridor, digital connectivity infrastructure by installing a fiber optic cable along the 750 kilometers corridor road, social amenities (boreholes, schools, and health centers), and emergency response facilities. The sample size for the study included all the 104 project teams involved in the implementation of HoAGDP in Kenya. Thus, a census survey was adopted since the sample was small but adequate.

Findings: The study found a positive significant influence between project communication planning and performance of HoAGDP in Kenya. The study also found a significant influence between schedule planning and performance of HoAGDP in Kenya. It therefore concludes that schedule planning significantly influences performance of projects.

Conclusions: The study concluded that project communication planning and schedule planning significantly influences performance of HoAGDP in Kenya

Recommendations: Regular feedback on issues and progress should be encouraged and formal method of communication should also be adopted where all the stakeholder will be receiving information concerning the project. The project manager should ensure the project schedule are detailed and updated since they form the basis of monitoring the project

Keywords: Project planning practices, communication planning, schedule planning, Horn of Africa Gateway development project, project performance.


Full Text:

PDF

References


Barinua, V., & Deinma, E. (2022). Time Management and Employee Engagement. BW Academic Journal, 1, 5-15.

Davis, F. (1989). Perceived usefulness, perceived ease of use, and user acceptance. MIS Quartely, 319-340.

Ezewuzie, J. J., Anazodo, O. G., & Agba, C. N. (2021). Effective time management in Nigerian schools: Challenges and Prospects. UNIZIK Journal of Educational Research and Policy Studies, 8, 39-45. https://unijerps.org/index.php/unijerps/article/view/234

Hassan, H. A. (2021). Ethnicity, Insecurity and Geostrategic Transformation in the Horn of Africa. Risks, Identity and Conflict: Theoretical Perspectives and Case Studies, 61-83.

Kerzner, H. (2022). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John wiley & sons.

Kozlowski, R., & Matejun, M. (2015). The identification of difficulties in using advanced technologies in the implementation of projects. International Journal of Business and Management, 3(4), 41-60.

Larsen, J.K., Lindhard, S.M., Brunoe, T.D., &Jensen, N.K. (2018). The relation between pre-planning, commissioning and enhanced project performance. International Journal of Quality Research, 11(1), 169-170.

Martins, J. (2024). Communication plan. Retrieved from asana.com: https://asana.com/resources/communication-plan

Matu, J., Kyalo, D., Mbugua, J., & Mulwa, A. (2020). Stakeholder Participation in Project Planning: Prerequisite to Effective Completion of Urban Road Transport Infrastructure Projects in Kenya. Journal of Building Construction and Planning Research, 8(1), 73-91.

Miringo, C. & Dushimimana, J.DD. (2023). Effect of project planning on project performance: A case of leasing project implemented by BDF in Kigali. Global Scientific journals, 11(2), 1317- 1340.

Odhiambo, A.A., Ouko, R.A., & Muhoho, J. (2020). Communications as a Driver of Performance of Projects in Kenyan Commercial Banks. International Academic Journal of Information Sciences and Project Management, 3(6), 100-112.

Office of the Auditor-General (2022). Report of the Auditor-General On Horn Of Africa Gateway Development Project credit number 6768-KE for the year ended 30 June 2023 -state department for roads. OAG.

Office of the Auditor-General (2023). Report of the Auditor-General on Horn Of Africa Gateway Development Project credit number 6768-KE for the year ended 30 June 2023 -state department for roads. OAG.

Ondiek, F. B. (2020). Influence of Project Panning on Road Construction Projects Performance in Uasin GIshu County, KENYA. Doctoral Dissertation. JKUA-COHRED.

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® guide) – and the standard for project management (ENGLISH) (7th ed.)

Rahimian, A., Hosseini, M.R., Martek, I., Taroun, A., Alvanchi, A., & Odeh, I. (2020). Predicting communication quality in construction projects: A fully-connected deep neural network approach. Automation in Construction, 139, 104-110. https://doi.org/10.1016/j.autcon.2022.104268.

Salman, A., Jaafar, M., Muhammad, S. A. (2020). An Empirical Investigation of the Impact of the Communication and Employee Motivation on the Project Success Using Agile Framework and Its Effect on the Software Development Business. Business Perspectives and Research, 9(1), 34-56. https://doi.org/10.1177/2278533720902915.

Tesfaye, E., Lemma, T., Berhan, E., & Beshah, B. (2016). Key Project Planning Processes Affecting Project Success. International Journal for Quality Research, 11(1) 159–172.

Tripathi, S. (2017). 'Understanding the determinants affecting the continuance intention to use cloud computing.'. Journal of International Technology & Information.

Venkatesh, V., Morris, M., Davis, G., & Davis, F. (2003). User acceptance of information technology: Toward a unified view. MIS Quartely, 27, 425-478.

Wanjau, C. M., Namusonge, G. N., & Lango, B. (2024). Project cost planning and performance of housing projects in Kenya. International Academic Journal of Information Sciences and Project Management, 3(7), 248-262.

World Bank (2020). International development association project appraisal document on a proposed credit in the amount of EUR 660. Million to the Republic of Kenya for a Horn of Africa Gateway Development Project. The World Bank Group.

World Bank (2023). Kenya - Horn of Africa Gateway Development Project (English).