PROJECT MANAGEMENT RISK PRACTICES AND IMPLEMENTATION OF RENEWABLE ENERGY PROJECTS IN GEOTHERMAL WELLS IN OLKARIA NAKURU, KENYA

Henry Mwendia Muchira, Dr. Benard Lango

Abstract


Purpose: The main objective of this study was to examine the influence of Project Risk Management Practice on the implementation of renewable energy Projects in geothermal wells in Olkaria Nakuru County, Kenya.

Methodology: This research was guided by a positivism paradigm as a research philosophy and adopted the descriptive research design since it utilizes elements for both the qualitative and quantitative in a study. the target population was 125 respondents and is comprising of the stakeholders in the geothermal industry ranging from the managers of drilling companies, the engineers, the rig operators, the community around the wells as well as government agencies involved in the drilling in Olkaria in Naivasha, Kenya. The study unit of observation was the 41 drilled wells currently in operation. A census was adopted as the sampling method across the population as most of the population across the industry is homogenous

Findings: The study found significant statistical evidence from the descriptive analysis to indicate the existence of Risk Management Planning influence implementation of renewable energy projects in geothermal wells in Olkaria Nakuru County. Risk Management Planning also had a positive significant influence on implementation of renewable energy projects in geothermal wells in Olkaria Nakuru County. Risk assessment was found to significantly influence implementation of renewable energy projects in geothermal wells in Olkaria Nakuru County by 0.365 or 36.5%. In addition, the findings indicated that risk assessment had a positive significant influence on implementation of renewable energy projects in geothermal wells in Olkaria Nakuru County.

Recommendations: renewable energy projects in geothermal wells in Olkaria Nakuru County should come have with well-structured document on how to conduct risk appraisals of all the projects before the commencement of the projects. The high-risk projects can either be avoided or mitigation measures put in place to address them from inception. Risk management function of renewable energy projects in geothermal wells in Olkaria Nakuru County is combined with internal audit function hence it lacks the independence to implement risk objectives effectively

Keywords: Project management practices, renewable energy projects, risk management planning, risk assessment


Full Text:

PDF

References


Attanasio, O.P., Guarin, A., Medina,C., Meghir, C. (2017). Vocational Training for Disadvantaged Youth in Colombia: A Long-Term Follow-Up. American Economic Journal Applied Economics 9(2):131-143. http://dx.doi.org/10.1257/app.20150554

Ayudhya, B. I., & Kunishima, M. (2019). Assessment of risk management for small resisdential projects in Thailand. Procedia computer Science, 164, 407-413.

Cawley, J. & Ruhm, C.J. (2011). The economics of risky health behaviours.IZA Discussion paper No 5728. https://dx.doi.org/10.2139/ssrn.1855160.

Cooper, D.R. and Schindler, P.S. (2014) Business Research Methods. 12th Edition, McGraw Hill International Edition, New York.

Dobson, M. S. (2015). Successful Project Management 4th Edition How to Complete Projects on Time, on Budget, and on Target. © 2015 American Management Association.

Doval, E. (2019). Risk management process in projects. Review of general management, 30(2), 97-113.

Harichandan, S., Kar, S. K. and Roy, B. (2022) ‘Policies, Strategies and Actions to Mitigate Energy Poverty in India’, Oil, Gas and Energy Quarterly, 70(4), p. 759.

Faiz, S. (2020). Impact of project risk management on project quality with the mediating role of project efficiency and moderating role of project culture. Master of science Thesis, Capital University of science and technology, Islamabad, Mangement Sciences.

ImaN, C., & Borimnejad, M. (2017). Effects of pf project risks panning on performance of Agaseke project in Kigali, Rwandi. International Journal of business and management review, 3(5), 29-51.

Kloppenborg, T. J. (2017). Contemporary Project Management, Third Edition. Cengage Learning.

Lester, A. (2017). Project Management, Planning and Control: Managing Engineering, Construction and Manufacturing Projects to PMI,APM and BSI Standards (7th ed.). Oxford OX5 1GB, United Kingdom: Elsevier Ltd.

Marzolf, N.C. (2014) Entrepreneurship of geothermal energy in Colombia,

Munoz, J.C, Sobrino, J.A., Skokovic, D., Mattar, C., Cristobal, J. (2014). Land Surface Temperature Retrieval Methods from Landsat-8 Thermal Infrared Sensor Data. IEEE geoscience and remote sensing letters, 11(10). 1840-1843

Sekaran, U., & Bougie, R. (2010). Research methods for business: A skill-building approach (5th ed.). Haddington: John Wiley & Sons.

PMI. (2017). A Guide to the Project Management Body of Knowledge: PMBOK Guide (6th ed.). Newtown Square, PA: Project Management Institute, Inc.

PMI. (2019). What is project management. USA: © 2019 Project Management Institute, Inc.

Rahman, M. S. (2018). Risk Management and Measurement of Risk management performance in complex projects. Master thesis, University of Oulu.