RESOURCE PLANNING PRACTICES AND PERFORMANCE OF DONOR-FUNDED WATER PROJECTS IN VIHIGA COUNTY, KENYA
Abstract
Background: The study aimed to examine the influence of resource planning practices on the performance of donor-funded water projects in Vihiga County, Kenya. The study specifically sought: to establish the influence of financial resources planning and to determine the influence of resource scheduling planning on the performance of water projects in Vihiga County, Kenya. The Resource-based view theory guided the study.
Methodology: The study adopted a cross-sectional survey design as a research design. The study focused on 14 water projects in Vihiga County in the last 5 fiscal years. The unit of observation was 304 respondents and a sample of 172 respondents comprising project managers, project team members, and project consultants.
Findings: The study found a positive strong correlation between financial resource planning and performance of water projects. However, resource scheduling had a weak significant correlation with performance of water projects. The study also established that financial resource planning positively and significantly influences the performance of water projects in Vihiga county in Kenya and resource scheduling planning positively and significantly influences the performance of water projects in Vihiga County in Kenya.
Recommendations: The study recommends a clear and defined budgeting process for projects. The study also calls for the application of scheduling techniques in projects to help realize project milestones.
Keywords: financial resources planning, resource scheduling planning, performance of water projects, Vihiga County, resource planning
Full Text:
PDFReferences
Ahmed, R. (2022). "Project Performance Measure and Metrics". In "Research Handbook on Project Performance" (pp. 11 -22). United Kingdom: Edward Elgar Publishing Limited.
Aldridge, E. (2023). Control Schedule in Project Management. Retrieved from projectmanagementacademy.net: https://projectmanagementacademy.net
Association for Project Management. (2018). APM Body of Knowledge, (6th ed.). Association for Project Management: Buckinghamshire.
Barney, J., & Ouchi, W. (1986). "Organizational economics". San Francisco: Jossey-Bass.
Doloi, H. (2013). "Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects". Journal of Construction Engineering and Management,, 139(3), 267-279.
Dopson, E. (2020). A project Manager's guide to resource planning in 2022. Retrieved 03 2022, from float.com: www.float.c0m
Głodziński, E. (2019). "Performance measurement of com ex roject framework and means supporting management of project-based organizations". International Journal of Information Systems and Project Management, 7(2), 21-34.
Jugdev, K., & Mathur, G. (2013). "Bridging situated learning theory to the resource‐based view of project management". International Journal of Managing Projects in Business, 6(4), 633-653.
Karuga, S., Utuku, M., & Sang, P. (2024). "Financial resource scheduling and road construction projects performance in Nairobi Metropolitan, Kenya". Research in Business & Social Science, 13(4), 223-229.
Kerzner, H. (2022). 'Project Management: A systems approach to planning, scheduling, and controlling' (13th ed.). New Jersey: John Wiley & Sons, Inc.
Maqsoom, A., Hamad, M., Ashraf, H., Thaheem, M. J., & Umer, M. (2020). "Managerial control mechanisms and their influence on project performance: an investigation of the moderating role of complexity risk". Engineering, Construction Architectural Management,, 27(9), 2451 - 2475.
Park, Y. J., & Yi, C. Y. (2021). 'Resource-based quality performance estimation method for construction operations'. Applied Sciences, 11(9), 4122.
PMI. (2017). A Guide to the Project Management Body of Knowledge: PMBOK Guide (6th ed.). Newtown Square, PA: Project Management Institute, Inc.
PMI. (2017). Guide to the Project Management Body of Knowledge PMBOK Guide 6th Edition. Newtown Square: Project Management Institute, Inc.
Ronoh, D. K., & Kirui, C. C. (2020). "Influence of Resource Scheduling On the performance of residential construction projects in Nairobi county, Kenya". International Journal of Research and Innovation in Social Science, 4(12), 409 - 414.
Sebasore, J., & Dieu, D. J. (2022). "Influence of planning practices on project success: The case of education project implemented by true. Voice of Research, 1(3), 22-32.
Suresh, D., & Sivakumar, A. (2019). Impact of Schedule Management Plan on Project Management Effectiveness. International Journal of Engineering and Advanced Technology, 9(1), 3350-33355.
Toe, S. (2023). 8 Project Scheduling Techniques Every Project Manager Must Know. Retrieved from runn.io: https://www.runn.io/
Umukumburwa, S. (2024). Local Financial Resources Planning and Construction Projects Performance in Rwanda. A Survey of Local Contraction Projects of Nyarugenge". International Journal of Novel Research in Humanity and Social Sciences, 11(1), 48-64. Retrieved from https://doi.org/10.5281/zenodo.10664594
UNICEF. (2020). "Water Scarcity". Retrieved from unicef.org: https://www.unicef.org/wash/water-scarcity
WASREB. (2023). "Impact-A Performance Report of Kenya’s Water Services Sector". Nairobi: WASREB.
Water Fund. (2024). "Finanicng the water sector". Retrieved from waterfund.go.ke: https://waterfund.go.ke/
Water Sector Reforms. (2019). "Financing of water sector in Kenya". Retrieved from waterreforms.go.ke: https://www.waterreforms.go.ke/financing-water-sector-in-kenya
Wernerfelt, B. (1995). The resource-based view of the firm: Ten years after. Strategic Managment Journal, 16(3), 171-174.
Westland, J. (2023). Resource Scheduling in project management. Retrieved from https://www.projectmanager.com: https://www.projectmanager.com/blog/better-resource-scheduling
Widowati, E. D., & Rachmawati, F. (2020). 'Identifying factors affecting schedule and cost performance on building project'. 4th International Conference on Civil Engineering Research (ICCER 2020) (pp. 1-10). IOP Publishing.
Zheng, L., Baron, C., Esteban, P., Xue, R., Zhang, Q., & Yang, S. (2019). "Using leading indicators to improve project performance measurement". Journal of Systems Science Systems Engineering, 28(5), 529 - 554.
Refbacks
- There are currently no refbacks.